After we wrote what estimation is, why it is important, and how to approach it, now we gonna take a look at some possible issues and useful guidelines for project evaluation.
It can happen that project managers resort to scheduling estimates in order to estimate the size of the overall project. This happens due to time constraints, i.e. deadlines that are determined mainly by management or by the marketing team.
However, for whatever reason, if it happens, then it is difficult to estimate the schedule at a later stage and adjust the change of the project scope. Even good estimates contain inherent assumptions, risks, and uncertainty – and yet, if they do, they are often treated as if they were accurate.
The best way to express estimates is through a number of possible outcomes.
For example, the project will last 5 to 7 months instead of stating that the project will be completed on a specific date or in a fixed number of months. Caution is required when committing to a timeline in a range that is too narrow because this is equivalent to setting a specific date. It can also be done to include uncertainty as an accompanying probability value. For example, there is a 90% probability that the project will be completed on or before a certain date.
The estimate may be questionable if the organization does not collect accurate project data because the accuracy of the estimate also significantly depends on historical data, so this may present a problem.
Each project has the shortest possible schedule that allows for the inclusion of the required functionality and production of quality results. If there is a schedule limit made by the management and/or the client, the scope and functionality need to be renegotiated accordingly, so it can be delivered.
It is important to agree with the client on the extent of management slowdown to avoid schedule overrun. Failure to accept contingencies in the final assessment causes problems. For example, meetings, organizational events, etc.
In addition to the above, resource use should be considered at less than 80%. This is because resources are productive for only 80% of their time. If more than 80% is allocated to resource utilization, there will inevitably be a slowdown in the project.
The following guidelines should be kept in mind when evaluating a project:
There are several assessment techniques. Here are some of them:
FP expresses the amount of business functionality of the information system or product provided. It is based on measuring software size. Thus, there is a widely accepted industry standard for functionality sizing, so-called ISO standards (International Organization for Standardization).
A series of related interactions between the user and the system that the user is allowed to achieve the goal. The use case checks the functional requirements of the system.
A structured communication technique, originally developed as a systematic, interactive prediction method that relies on a panel of experts.
As the name suggests, it includes three value elements: the most optimistic estimate (O), the most probable estimate (M), and the pessimistic estimate, that is, the least probable estimate (L).
E = (O + M + L) / 3
This assessment takes into account three values: the most optimistic estimate (O), the most probable estimate (M), and the pessimistic or least probable estimate (L). It is very similar to the three-point estimation, so there is very often confusion if both of them are not known well enough, or how they work has not been explored well enough.
E = (O + 4 × M + L) / 6
Used to calculate data on a similar project to estimate the duration or cost of the current project. The estimate you can use is just limited information when evaluating the current project.
Project decomposition focused on the delivery of smaller components. WBS is a key result of a project that organizes the work team into manageable parts. WBS elements can be product, data, service, or a combination thereof. WBS also provides the necessary framework for detailed cost estimation and control while providing guidance for schedule development and control.
Combines three assessment methods: The Wideband Delphi Technique, Analogous Estimation, and WBS.
While estimating, there are many different reasons that can cause some issues, so it is important to express estimates in a number of possible outcomes. This is one of the reasons why it is important to keep in mind the estimation guidelines mentioned above, no matter which of the described estimation techniques you choose.